Another such finished ‘cut’ is seen between Medziphema and Nagaland Police Check Post in these photos taken September 24. (Morung Photo)
The SARDP-North East (Special Accelerated Road Development Programme) Project under Engineering, Procurement and Construction (EPC) mode is being constructed under three packages (excluding Dimapur & Kohima Bypass).
However, the works are going beyond deadline for various reasons. According to a Raj Bhavan Kohima document, the date of completion “as per contract agreement” for Package I-III was on September 15, 2019. Information on the National Highways and Infrastructure Development Corporation’s (NHIDCL) website on the “Current Status” of its projects in Nagaland stated that while Package I and II are supposed to be finished by 31.03.2021, the contract for Package III has been “Terminated” and “Re-tendered awarded for the balance work.” Meanwhile, in a reply to a starred question in the Lok Sabha on July 22, 2021, Union Minister of Road Transport and Highways Nitin Jairam Gadkari informed that the progress of the works for Package I and II are “On Schedule” without giving a deadline, while Package III was “re-tendered award for the balance work.” The progress of works for Package I, II& III then were 84.10%, 88.64% and 71.69% respectively. As inferred from observing the physical progress on September 24, the completion of the project, at face value, still remains an uphill task.