    Need for proper SOP specific to search operations in Doyang highlighted    Wokha, July 15 (MExN): Wokha District Disaster Management Authority (WDDMA) held a meeting to discuss on disaster during monsoon season at DCs conference hall, Wokha on July 15.  According to a DIPR report, Deputy Commissioner & Chairman WDDMA, Orenthung Lotha who chaired the meeting, in his opening remark said that due to COVID-19 lockdown, all the other activities have been stalle
  • Foothills Road: Doyang bridge 70% done after 5-plus yrs
    Morung Express News Dimapur | July 11 The Doyang bridge, a key link in the long awaited Trans-Nagaland Expressway – erstwhile known as the Nagaland Foothills Road Project – is said to be 70 percent complete after 5 and half years of construction. The construction of the 2-lane RCC beam bridge, located in Liphanyan (Ralan area, Wokha), had started in December 2014 with a 33-month completion timeframe. The Nagaland Foothills Road Coordination Committee (NFHRCC) inf